ERECTION OF THE SPACE FRAME PURLIN
Add Time:2014-03-17 Hits:1725num
The sequence for the erection of the space frame purlin:Erection of the
purlin support→Erection of the main purlin→erection of the secondary purlin.
1 Fasten the purlin support onto the bolt ball of the
space frame in accordance with its number marked by the
drawing,fastening it tightly and levelling it.As the top of the dome is
rather flat,and highly leakable, heighten the last three circles of
purlin suppor proportionately,increase the degree of the slope,raise the
top for 150mm, and raise the second circle for 100mm ,and the third
ring for 50mm.
2 Fasten the connecting board of the principal purlin
to the principal purlin with the bolt.Adjust the principal purlin to the
right position as design requests,and weld it onto the purlin support
with the connecting board. The folded edges of the main purlin must face
the same direction according to requirement,after the welding is
finished,fasten the connecting bolt tightly
by twisting it.
3. Fasten the connecting bar of the subpurlin to the
two ends of the subpurlin with the bolt,and then fasten it to the
corresponding principal purlin in order of the number marked by the
drawing
4.After erection is finished,all the purlins should be
flattened,straightened,fastened,and then repaint the welded part